Chris Flavin tells Semafor that investors are ready to fund African electricity projects, but too few developers can navigate the years of permitting and planning required to reach financial close—and mining customers offer the demand certainty that household connections lack
Africa’s electricity expansion is being constrained less by a shortage of investment capital than by an insufficient number of project developers capable of preparing infrastructure projects for financing, according to Chris Flavin, chief executive of Gridworks, the UK government-backed power developer and investor.
Speaking to Semafor, Flavin pushed back against the conventional narrative that Africa’s power deficit is fundamentally a capital problem. “People spend a lot of time talking about a lack of capital for infrastructure projects in Africa. There is not a lack of capital,” he said . The issue, he argued, is structural: investors generally want to get involved once projects are ready for construction, leaving the four or five years of preparatory work—permits, environmental approvals, and planning—harder to finance.
Gridworks, which develops and invests in electricity networks across Africa, faces the same hurdles as other developers despite its UK backing. Flavin described the process as involving years of planning “before you even get close to the financing” . In the Democratic Republic of Congo, commercial banks will not lend at that early stage, according to Archip Lobo, co-founder of Nuru, a solar mini-grid operator in the country’s east. “They will take the risk on something that exists,” Lobo told Semafor .
The Industrial Advantage
Flavin noted that private power projects in Africa are easier to develop when they serve large industrial buyers, particularly mining companies, rather than households and small businesses. A mine with a strong balance sheet and known electricity consumption gives developers a clear customer to design around. For projects aimed at individual customers, “the challenge is one of guaranteed demand,” Flavin said .
This dynamic was illustrated in southeastern DR Congo, where CrossBoundary Energy, a Mauritius-based power producer, commissioned a 233-megawatt solar farm with battery storage in August to supply the Kamoa-Kakula copper complex co-owned by Ivanhoe Mines. Auguy Bakome, a project manager at the mine, told Semafor that its expected 40-year operating life and a 15-year contract to buy the electricity helped reassure lenders .
Gridworks itself is set to become the majority shareholder in a planned $300 million power line linking Zambia’s grid to DR Congo’s copper-mining region, under an agreement signed in October. Lenders have shown “very strong interest” in the line, Flavin said . The Kalumbila–Kolwezi Interconnector Project will carry up to 700 MW of power into Katanga, helping address a regional electricity deficit of more than 1 GW . Flavin has said the line, while anchored by mining offtake, will have capacity to serve the wider population .
Utilities, by contrast, must estimate consumption across tens of thousands of customers. Building networks to serve them is “at the much harder end of the spectrum, full stop,” Flavin said . Moyi Power, a Gridworks-backed utility planned for three cities in northern DR Congo, relies on donor grants for about a quarter of its $190 million first phase and is not expected to deliver electricity before 2029 .
A Dissenting View on Capital
The World Bank’s own evaluators have taken a less optimistic view of capital availability. A recent review found that private financing remained too limited to meet Africa’s electrification needs, and that the narrow pool of investors—development lenders’ private arms, government-sponsored funds, foundations, and impact funds—”are unlikely to meet the scale of financing needed for electrification growth,” according to Semafor’s reporting .
The Access Gap
More than 40% of sub-Saharan Africans lack electricity. A World Bank and African Development Bank initiative, Mission 300, is working to bring electricity to 300 million of the continent’s inhabitants by 2030 . The initiative, launched in April 2024 and endorsed by African heads of state in January 2025, aims to connect 250 million people through the World Bank Group and 50 million through the African Development Bank . As of June 2026, Mission 300 had connected over 50 million people across 40 countries, with the World Bank Group and AfDB committing nearly $15 billion in financing and attracting about $4.5 billion in co-financing .